Week 9 Activity – Project
Week 9 Activity – Project Performance Measurement & Closure
Overview
With the communication issues stabilized, the focus turns to project performance measurement and closure. Chapter 13 presents a discussion on metrics used to assess project performance. Three commonly used metrics are schedule variance (SV), cost variance (CV), and cost performance index (CPI). The sponsor is not familiar with how these metrics work and has asked for a demonstration of how they are used. The sponsor has presented a scenario and is requesting you to conduct a demonstration using fictitious data to access the results given the following situation.
Instructions
On day 51, a project has an earned value of $600, an actual cost of $650, and a planned cost of $540. Compute the SV, CV, and CPI for the project. Present your results and explain them.
Next, the project sponsor wants to be assured that the project will be closed in accordance with best practices. Research what the Project Management Body of Knowledge (PMBOK) says about closing projects and briefly discuss.
nowurgent
We've got everything to become your favourite writing service
Money back guarantee
Your money is safe. If we fail to satisfy your expectations, you can always request a refund and get your money back.
Confidentiality
We don’t share your private information with anyone. What happens on our website stays on our website.
Our service is legit
We provide you with a sample paper on the topic you need, and this kind of academic assistance is perfectly legitimate.
Get a plagiarism-free paper
We check every paper with our plagiarism-detection software, so you get a unique paper written for your particular purposes.
We can help with urgent tasks
Need a paper tomorrow? We can write it even while you’re sleeping. Place an order now and get your paper in 8 hours.
Pay a fair price
Our prices depend on urgency and level of study. If you want a cheap essay, place your order with as much time as possible. Our prices start from $11 per page.