Resource Scheduling

A project has 11 activities that can be accomplished either by one person working alone or by several people working together. The activities, precedence constraints, and time estimates are given in Table below. Suppose that you have up to five people who can be assigned on any given day. A person must work full days on each activity, but the number of people working on an activity can vary from day to day.
   
Activity

Immediate predecessors

Don't use plagiarized sources. Get Your Custom Essay on
Resource Scheduling
Just from $13/Page
Order Essay

Person-days required
 
A

10
 
B

A

8
 
C

A

5
 
D

B

6
 
E

D

8
 
F

C

7
 
G

E,F

4
 
H

F

2
 
I

F

3
 
J

H,I

3
 
K

J,G

2

Prepare an AOA network diagram, and calculate the critical path, total slacks, and free slacks assuming that one person (independently) is working on each task.
Prepare an early-start Gantt chart.
Prepare a daily assignment sheet for personnel with the goal of finishing the project in the minimum amount of time.
Prepare a daily assignment sheet to “best” balance the workforce assigned to the project.
By how many days could the project be compressed if unlimited personnel resources were available?

Calculator

Calculate the price of your paper

Total price:$26
Our features

We've got everything to become your favourite writing service

Need a better grade?
We've got you covered.

Order your paper
Live Chat+1(978) 822-0999EmailWhatsApp

Order your essay today and save 20% with the discount code SEARCHGO