Management, Information, Technology

  
System Integration Project  
Application of PERT/CPM  
Two international banks are integrating two financial processing software systems as a result of their merger. Preliminary analysis and interviews with all parties involved resulted in the following project information. The “systems integration team” for this project plans to define and manage this project on two levels. The following activities represent an aggregate view, and within each activity is a more detailed view with subtasks and project networks defined. All times are in weeks.
Activity           Immediate                   Time
                        Predecessors
A                         —                                 3 
B                         A                                  1
C                         A                                  2 
D                       B, C                               3 
E                        C                                   5
F                         C                                  3 
G                        E                                   7 
H                       E, F                                5 
I                      D, G, H                             8

As a member of the systems integration team, you have operations management
responsibilities. You have been tasked to develop a detailed project plan, to 
identify alternative project completion dates, and to recommend an optimal project
deadline to top management.

Don't use plagiarized sources. Get Your Custom Essay on
Management, Information, Technology
Just from $13/Page
Order Essay

You should start with a Gantt Chart that will keep top management temporarily
 content, while you prepare your PERT/CPM analysis. You need an Activities Time 
Requirements Table, a Critical Task and Slack Time Table, and a PERT/CPM 
Network Diagram that displays the critical path. Of course, you will prepare a
report for top management with the Background of this systems project, the project 
deadline Issue to be resolved, the three project deadline Alternatives, an
Analysis of the three Alternatives, and your Recommendation.

Attached to your report should be a Gantt Chart, Activities Time 
Requirements Table, a Critical Task and Slack Time Table, and a PERT/CPM 
Network Diagram – 4 Attachments.

Calculator

Calculate the price of your paper

Total price:$26
Our features

We've got everything to become your favourite writing service

Need a better grade?
We've got you covered.

Order your paper
error: Content is protected !!
Live Chat+1(978) 822-0999EmailWhatsApp

Order your essay today and save 20% with the discount code SEARCHGO