Question 1. The first step in planning and scheduling a project is to develop the __________.
Student Answer: 
employee scheduling plan
PERT/CPM network diagram
critical path
work breakdown structure
variance calculations for each activity
Question 2. The critical path of a network is the:
Student Answer: 
shortest time path through the network.
path with the fewest activities.
path with the most activities.
longest time path through the network.
none of the above.
Question 3. PERT:
Student Answer: 
assumes that we do not know ahead of time what activities must be completed.
assumes that activity time estimates follow the normal probability distribution.
is a network technique that uses three time estimates for each activity in a project.
is a deterministic network technique that allows for project crashing.
None of the above is correct.

Don't use plagiarized sources. Get Your Custom Essay on
GBA334 Final Exam Latest/GBA334 Final Exam Latest/GBA334 Final Exam Latest
Just from $13/Page
Order Essay
Calculator

Calculate the price of your paper

Total price:$26
Our features

We've got everything to become your favourite writing service

Need a better grade?
We've got you covered.

Order your paper
Live Chat+1(978) 822-0999EmailWhatsApp

Order your essay today and save 20% with the discount code SEARCHGO